REHABILITATION OF KIGALI AIRPORT, RWANDA
REHABILITATION OF KIGALI AIRPORT, RWANDA Facts Project Description Second phase of airport rehabilitation in Kigali, capital of Rwanda, Lot 1.1 + 1.2 Rehabilitation of 3.7 km long and 60 m wide runway of Kigali Airport as well as extensive works on apron and several infrastructure facilities. PROJECT DATA: Earthworks 250 000 m3 Milling of pavement 59 000 m2 Bituminous Concrete 50 496 t Bituminous Base Course 12 186 t Prime coat 59 625 m2 Tack coat 367 175 m2 Anti-kerosene protection 43 750 m2 Pavement marking 15 300 m2 City/Country Kigali / Rwanda Client Ministère des Finances et da la Planification économique Architect Ministère des Finances et da la Planification économique Contract Value € 11,80 Mio. Construction Period 2/2004 - 2/2005 (12 months) .