REHABILITATION OF WAHNBACH DAM

REHABILITATION OF WAHNBACH DAM

REHABILITATION OF WAHNBACH DAM Facts Project Description The existing dense asphalt lining is removed up to the lower storag level and replaced by a fresh asphalt lining. Transitions to old liner are tempered and receive strengthening layer on top. Perimeter joints against concrete walls / plinths are renewed. Bituminous mastic seal is applied for ageing protection. Project Data: Reservoir capacity: 41 Mio m3 Total lining surface (1:1,52): 25,500 m2 New dense asphalt course: 11,500 m2 New mastic seal: 14,000 m2 Works: Milling of old asphaltic lining: 5 - 6 cm New dense asphaltic lining: 7 cm Edge strenghtening layer: 6 cm New construction joint: 30 m Placing of mastic seal: 2 kg / m2 Asphalt concrete sealing with an inclination of 1:1.5. City/Country Wahnbach / Germany Client Wahnbachtalsp