PROJECT PROFILE Summary 10,000m 2 of concrete runway and taxiway at Gimpo, South Korea’s number 2 airport, suffered from varying degrees of subsidence, from 50mm to 160mm. The subsidence meant that the surface design stormwater profiles were no longer effective. Ponding after rain created ice patches, which could cause aircraft to skid. The project was completed with precision in 28 days by Uretek Slab Lifting bringing the surfaces back to