Case Study
A1 Coal House improvement
Dutypoint Ltd, Shepherd Road, Gloucester GL2 5EL T: 01452 300592 E: sales@dutypoint.com W: www.dutypoint.com PROJECT SUMMARY Dutypoint were contacted by the main contractor to assist in a pre-packaged pump station to collect storm water from the new drainage scheme in a 1:100 year storm. Storm water in a freak storm would rise over a weir in the drainage system and divert through the pump station. PROJECT CHALLENGE The pump station was not initially within the scope of this project so the client was looking to install something as quickly and competitively as possible. They contacted us to assist in designing a pre-packaged system to keep their costs and program as low as possible. When the drainage system was completed, it became apparent that this was not going to be within th