Turning Up The Heat, At The Worcester Headquarters

Turning Up The Heat, At The Worcester Headquarters

CASE STUDY www.oaklandgroup.com PROJECT DETAILS The existing 2No Hoval gas boilers serving the factory were over 30 years old and the plant was ageing. One of the boilers had finally succumbed to damage and so the decision was taken by Mazak to replace it with new, more efficient plant. Two high efficiency forced draft sectional 920kw boilers supplied by locally based Worcester Bosch were chosen by Mazak to replace the old appliances. Oakland Air Control Ltd were given the order to replace Boiler No 2 which was fully installed by January 2018. Due to a requirement for strict operating conditions on the new boilers and to further improve the system efficiency a full plant room refurbishment was necessary. An upgrade of the ancillary plant and Trend control panel was also req