Case Study : Aberdeen Torry Quay Phase 3 Silt Curtain Client: Aberdeen Harbour Board Contractor: McLaughlin & Harvey Duration: 54 weeks Value: £13,000,000 Engineer: Arch Henderson Aberdeen Port is the centre of the offshore oil and gas industry’s marine support operations in North West Europe as well as a base for companies servicing the offshore renewable industry. Annually handling around 5 million tonnes of