Case Study
Top Quality in Next to No Time Thanks to VÖGELE
29,000t of mix were delivered by a fleet of 60 feed lorries. Top Quality in Next to No Time Thanks to VÖGELE Pavement rehabilitation of the runway at Bremen City Airport, Germany. One of the most spectacular construction projects of the last summer took place at Bremen City Airport: the airport’s only runway was in urgent need of rehabilitation as it was over 20 years old and pitted with holes and cracks. The parties responsible had only one option – to close the airport for the duration of the pavement rehabilitation work. This made it even more important to reduce the actual construction time to an absolute minimum. The contract for the works was awarded to Heitkamp Erd- und Straßenbau GmbH, who already had experience in runway rehabilitation projects. One of the tasks involved was the p