Case Study
The proposed housing development required a surface water pumping station with a rising main to discharge into the public sewer.
The proposed housing development required a surface water pumping station with a rising main to discharge into the public sewer.
How can we support your development project? T: 01824 702220 E: enquiries@waterco.co.uk WASTEWATER NON-INFRASTRUCTURE SOLUTION The Scope The proposed housing development required a surface water pumping station with a rising main that had to cross third party land to discharge into the public sewer. As such, the Developer Macbryde Homes could not construct the surface water rising main and had to requisition this sewer from Dwr Cymru Welsh Water (DCWW) Developer Services. Waterco were engaged directly by DCWW to deliver the requisitioned works design which included the pumping station. Client: DCWW Developer Services Scheme: Belvedere Park, Neston The pumping station served as the site SuDS, to comply with the restricted discharge for the development (5l/s) as required by the