Sussex 7-Day Railway Hookswitch Replacement Project
“The principle behind the project was to allow quicker and safer isolations for Network Rail Maintenance and Projects” Controlled Track Switch (CTS) P od-Trak were contracted to supply, install and commission all the ETE within and beyond the project footprint. Purley is a very busy outer London hub linking Brighton and the South Coast to London. The Renewals were one of the largest undertaken in the south with such short delivery timescales. 17-point ends and extensive plain line renewals were installed and commissioned within a 10-day Christmas / New Year Blockade. All ETE Materials, Tooling, Plant and Labour was supplied by Pod-Trak. Within a 10 day blockade the Pod-Trak ETE teams delivered all ETE associated to the project. This included installation of all