Arun Valley Lines - Re-Signalling
“18 miles of Negative bonding and associated ETE Successfully Commissioned in a single weekend” Arun Valley Lines - Re-Signalling Arun Valley Lines - Re-Signalling Pulborough Signal Box with semaphore signal now de-commissioned P od-Trak were contracted to supply and install all the ETE associated to the Arun Valley re-signalling project. The Arun Valley re-signalling project was an 18 mile up-grade of the aging signalling system which even included the almost extinct semaphore signals. To facilitate the upgrade various aspects of the ETE configuration required modification and / or renewal. The works included extensive negative bonding enhancements, replacement and alterations. This would include upgrading and bringing the existing DC 150sqmm and 240sqmm aluminiu