Case Study

Conductor Rail Renewals

Conductor Rail Renewals

Pages 1 Pages

“2km of new 150lb/75kg conductor rail and associated ETE installed in one weekend possession” Conductor Rail Renewals Conductor Rail Renewals All OTP supplied by Pod-Trak Ltd P od-Trak were contracted to deliver all ETE associated to the Kent Package 1 conductor Rail Renewals and Insulator Pot Replacement Project. The conductor rail renewals were undertaken within the surrounding coastal areas including Bexhill, West Marina and Cooden Beach. The extensive Insulator Pot replacement programme was undertaken in very busy London Terminus Stations such as Cannon Street and Charing Cross. All ETE Skilled staff, On Track Plant and tooling were supplied by Pod-Trak Ltd. Working from AFC designs our ETE teams delivered numerous conductor rail renewals to time, budget and N

Join for free to read