Strengthening the ‘best port in the world’s’ reputation

Strengthening the ‘best port in the world’s’ reputation

Visit us at graham.co.uk £4m / Project value July 2015 / The build commenced March 2016 / The build was completed Described as a ‘one-off opportunity for the regeneration of Dover’, the Dover Western Docks Revival project is primed to increase the development of the port’s cargo business, create greater space for ferry traffi c and enhance the business appeal of the waterfront. Our Early Contractor Involvement (ECI) Phase 1 works, incorporating an enabling works programme based at the Hoverport and the Prince of Wales Pier, have made an important contribution to the overall scheme within Europe’s busiest ferry port. Signifi cantly, we generated 17% of cost savings during ECI Phase 1, reducing the target cost from an initial £127m to £105m. The Brief Dover Harbour Board (DHB)