Case Study

INTERMOOR OVERCOMES OPERATIONAL CHALLENGES TO INSTALL PRE-LAY MOORING NEAR INDONESIAN SHORELINE

INTERMOOR OVERCOMES OPERATIONAL CHALLENGES TO INSTALL PRE-LAY MOORING NEAR INDONESIAN SHORELINE

Pages 2 Pages

Project Name: Nearshore mooring at BOMC Location: Bintan Offshore Marine Centre (BOMC) Region: Riau Islands, Indonesia Water depth: Shore to 30m Date: Q1 2021 THE PROBLEM The rigid reel lay vessel was to be moored at BOMC for reeling operations. An offshore mooring system needed to be pre-laid at the site to later hook up to it. The client needed: ? Project management, engineering and crew for transportation and installation of the mooring pre-lay system ? Charter of one Anchor Handling Tug Supply (AHTS) vessel for transportation and installation of the mooring system ? Managing manpower and logistics for the transportation and installation phase ? Engineering of the mooring design for catenary checks and buoyancy optimisation ? Procurement and preparation of mooring equipment U