Case Study

SURF INSTALLATION PROJECT COMPLETED AHEAD OF SCHEDULE DURING MONSOON SEASON

SURF INSTALLATION PROJECT COMPLETED AHEAD OF SCHEDULE DURING MONSOON SEASON

Pages 1 Pages

Project name: Mampu-1 FPSO ESP Installation Location: AJK Field (168km North-West offshore Bintulu and 30km South-East of Kumang Gas Field) Region: Sarawak, offshore Malaysia Client: MISC Offshore Floating Terminals Dua Ltd (MOFT2), a subsidiary of MISC Berhad Work scope: Project management, engineering and offshore operations for the installation of • one electric submersible pump (ESP) power generation module on FPSO MAMPU-1 • one chute support structure at the Tarpon platform • one shelter structure at the Tarpon platform • install/laying 1.26km of subsea power cable between FPSO MAMPU-1 and Tarpon platform. THE PROBLEM InterMoor was contracted by MOFT2 for the provision of upgrading MAMPU-1 and modification at Anjung Kecil (AJK) wellhead platform offshore installation. The