Case Study
House Re-supported And Re-levelled
PROJECT PROFILE Summary Unprecedented summer rain, of more than 300mm a week, caused extreme saturation of the soil under this large, new Queensland house set on concrete strip footings. The house had subsided by an average 45 mm! Uretek Deep-Injection was able to compact the soil and the Slab-Lifting method brought it back to exact level in just three days. Objectives To compact the sodden sub-base ground and re-level the strip footings o