Contract Management: PFI Case Study

Contract Management: PFI Case Study

Pages 1 Pages

Contract Management: PFI Case Study NHS Trust “SSG has given the Trust a sustainable approach going forward for re-setting the contract management framework” Director of Finance CONTRACT RESET REQUIRED Annual £9.2m unitary charge. Lack of transparency regarding life cycle spend. Strained working relationship with the PFI Prop Co, shared contract management rigours required to address poor performance absent. Greater knowledge and experience of managing PFI contracts needed to reduce errors pursuing claims through the contract dispute process. The Trust had incurred £3.6m to resolve CQC notices for reduced ligature with more spend planned. DIAGNOSTIC SSG conducted an intense but swift review, including examination of underlying contract variation data, analysis of legal re