Case Study
Codsall Drainage
A section of track northwest of Codsall Station in South Staffordshire had poor drainage and unable to cope with heavy persistent rain. As a result, the commuter services to and from Wolverhampton and Birmingham were becoming unreliable. Pod-Trak were contracted to construct an access road, set up the compound and complete all drainage works. Once land access was agreed with the landowner, Pod-Trak made an opening in the hedge, installed a stock fence and a temporary access road & compound using the dura-base system from Terrafirma Roadways to minimise impact and damage to the land. Site setup included all welfare and offices. The on track drainage consisted of 700m of 300mm diameter HDPE drainage pipe with 14 chambers. To support the existing flow from adjacent l