Skanska appointed Clifford Devlin to carry out the enabling works at Borough Viaduct which involves the demolition of several structures to make way for a new section of viaduct and accommodate additional through traffic from London Bridge Station. The project, which is part of the £5.5 billion Thameslink programme, is designed to upgrade London Bridge Station and allow for an extra 50 percent rail capacity at peak times. The enabling works were sequenced in four distinct phases: Phase 1: 16-26 Borough High Street Following the strip out of various arches and removal of a few small structures (to make way for piling works) we commenced the demolition of a block of four-storey buildings on Borough High Street. Demolition was carried out in a careful, progressive manner on a top-down, floor-