Case Study

10 MW Power Plant | Liberia

10 MW Power Plant | Liberia

Pages 2 Pages

10 MW Power Plant | Liberia Liberia’s civil war devastated the country’s infrastructure and left Monrovia, Liberia’s capital city, without stable electric power. Private generators have been operating on fuel since then, but have not been able to run e?ciently, leaving several communities in darkness. Challenge Under an emergency rehabilitation program funded by the U.S. Agency for International Development (USAID), a new power plant was required to provide more commercial power to Liberia on a fast-track basis. The plant required rapid delivery, with a schedule from contract award to inauguration in just eight months. Solution Louis Berger delivered a 10 MW turnkey power plant for Liberia Electricity Corporation at Bushrod Island within the accelerated schedule. Amid the challenges posed

Join for free to read