Case Study

Underground Piping Repair

Underground Piping Repair

Pages 1 Pages

Underground Piping Repair Case Study Facility: Resort Condominium Repair Parameters: Replace broken underground schedule 40 PVC piping. Repair Challenges: Structural & Mechanical Engineering required for new piping configuration. Repair Rigging & Tools: New Aquatherm Greenpipe® polypropylene pressure piping system was installed, with heat welded connections and joints used as a superior long term cost effective solution. Repair Time / Constraints / Opportunities: The Cooling Tower was originally installed lower than the piping in The Mechanical room causing the pump to lose prime when the chiller shutdown. We relocated the condenser pump, installing the piping lower than the tower solving the problem. Th