Case Study

The Heath High School

The Heath High School

Case Study The Heath, Runcorn Project Name The Heath High School Client Carillion Commenced August 2016 Duration Phase Completed December 2017 – Phase 2 January 2019 The Project The Heath High School is currently being rebuilt, with a capacity of 1,250 pupils. The new school building will include a sports and community centre, activity hall, dance and drama studios and a café. Throughout the grounds, there will be new external features. This includes tennis courts, multi-use game areas, an amphitheatre and dining terrace. The building will house a sixth form and specialist laboratories, workshops and classrooms ‘befitting a 21st century school’. Scope The Scope of Works is broken down into the following sections: • Access road and car park – Ac