Case Study

Blundell Street, Liverpool

Blundell Street, Liverpool

a Case Study Blundell Street, Liverpool Project Name Blundell Street, Liverpool Commenced October 2018 Duration Phase 1 – January 2019 Phase 2 – August 2019 The Project In the Baltic Triangle, Murraywood have been appointed the groundworks package. The project is a nine story-high apartment block with 200 apartments consisting of one, two and three bed apartments. There will be an underground car park, retail space (393m2) and office space (160m2). Scope The scope of works is broken down into the following sections: - • Attenuation Tank • Basement Slab • Foundation Bases • Foul and Surface Water Drainage • Off Site Drainage Connection • Perimeter Concrete Retaining Wall • Tower Crane Base