Case Study
St Georges Park , New FA Headquarters, Burton
Murraywood Construction Ltd Case Study - St Georges Park, New FA Headquarters, Burton Project : St Georges Park - New FA Headquarters and Training Facility, Burton Client: Bowmer & Kirkland Total Project Value: £105 Million Subcontract Value: £6.25 Million Commenced: February 2011 Duration: 72 Weeks Scope: Full groundworks package in order to construct the new National FA Headquarters, St Georges Park, Burton. • Large reinforced foundations and associated ground beams. • Large piled foundations. • Foul and surface water drainage systems with excavations reaching up to 9m deep. • Over 20,000 linear metres of buried services to serve the complex. • 450m of 4m high retaining walls to form basements and retaining landscap