Case Study
Temporary solution goes with the flow
Water companies require non-interruption of services via seamless operation to keep the flow flowing, when vital repairs are necessary. That’s where solutions expertise and industry understanding of 24/7 requirements for vital resources allowed Selwood to step in, by providing a temporary pumping station for a collapsing mains which was being replaced by Thames Water. Working in partnership with Morrisons Utility Services & Galliford Try (MGjv), a joint venture awarding meter installation activities across the Thames Water area, Selwood drew on both product knowledge and industry understanding to construct a temporary pumping station. This solution involved setting up two 33,000 litre tanks capable of providing 66,000 litres of storage for around two minutes before flooding. To achieve a f