250kW Temporary Packaged Boiler Solution Ram Brewery Project Objective Our client was the Senior Quantity Surveyor of a large energy services company. Construction of a large property development was in progress with some apartments approaching completion. The client required a temporary boiler to be connected to one of the buildings which contained twelve flats on three floors. The boiler was needed for two purposes, initially for screed drying in the apartments and later on, to provide heat to more buildings within the development. A temporary 250 kW boiler was specified to provide Low Temperature Hot Water (LTHW) to the site. The 250kW boiler gave the client enough extra capacity to open up other parts of the heating circuits to feed further buildings on the development.Briefing The boi