TEAM Turns Up the Heat for Esso

TEAM Turns Up the Heat for Esso

Pages 1 Pages

TEAM Turns Up the Heat for Esso Project: Custom Design of Heat Exchanger with Tight Deadline Location: Esso Plant in Ingolstadt, Germany TEAM Service: On-Line Leak Sealing and Repair Need and Challenge: The Esso process and refining plant based at Ingolstadt in Germany, required a dedicated heat exchanger designed in a U-shaped configuration for their planned shutdown/start up. The problem was that their existing heat exchanger failed and needed replacing. To keep the planned shutdown on schedule they needed the new exchanger in double quick time – just six weeks, when the normal production lead-time is closer to three to four months. Solution and Outcome TEAM designed and manufactured the specification and confirmed the cost in just 24 hours. Six weeks on, the new heat excha