Case Study

Snetterton Renewable Energy Plant, UK

Snetterton Renewable Energy Plant, UK

Pages 2 Pages

SNET TERTON RENEWABLE ENERGY PL ANT, UK Case stories - BWE BoilersBurmeister & Wain Scandinavian Contractor A/S Gydevang 35 ? DK-3450 Allerød ? Denmark Phone: +45 4814 0022 ? bwsc@bwsc.dk ? bwsc.com BWSC-30-0037-rev02-04/18 Boiler data Steam 173 t/h, 112 bar and 540°C Boiler efficiency 91.8% (EN 12952-15) Heat input 130 MJ/s Foot print 34.0 m x 33.9 m Boiler house height (internal) 32 m C A SE STORIES - BWE BOILERS ECO2 Lincs Ltd. chose a BWE Boiler for the complete greenfield straw-fired biomass plant located in Snetterton, UK. Plant capacity is 44 MWe and has a net plant efficiency of 34%. The contract was awarded in November 2014 and expected to be completed in September 2017. The plant The Snetterton Renewable Energy Plant (Snetterton REP) was built for production of electricity