Cramlington Renewable Energy Plant, UK

Cramlington Renewable Energy Plant, UK

Pages 2 Pages

CR AMLINGTON RENEWABLE ENERGY PL ANT, UK Case stories - BWE BoilersBurmeister & Wain Scandinavian Contractor A/S Gydevang 35 ? DK-3450 Allerød ? Denmark Phone: +45 4814 0022 ? bwsc@bwsc.dk ? bwsc.com BWSC-30-0037-rev02-04/18 Boiler data Steam 90 t/h, 140 bar and 540/540°C Boiler efficiency 91.7% (EN 12952-15) Heat input 78 MJ/s Foot print 26.5 m x 32.0 m Boiler house height (internal) 32 m C A SE STORIES - BWE BOILERS Estover Energy, John Laing and Green Investment Bank chose a BWE Boiler for the greenfield wood chip fired biomass plant located in Cramlington, UK. Plant capacity is 26 MWe + 6 MWth, the plant has a net plant efficiency of 35.6%. The contract was awarded in November 2014 and was completed in April 2017. The plant The Cramlington Renewable Energy Plant (Cramlington R