Case Study
Printworks: Building 5
KEY FACTS CASE STUDY - LEEDS CITY COLLEGE PRINTWORKS: BUILDING 5 HEADLINES PRAISED education facilities worked on simultaneously by client and contractor for our consideration working in a live environment Project title: Printworks: Building 5 Location: Leeds Client: Leeds City College Services: Mechanical & Electrical Contractor: Sewell Group Value: £650,000 Duration: 24 weeks G&H divisions: Building Services to change the building’s use from hairdressing classrooms to motor maintenance workshops 24 2 WEEKS LIVECASE STUDY HOW WE DID IT This required a high level of liaison with the main contractor. We overlapped the schemes to complete our work in B1 by the end of the May holiday period and delivered the most invas