Halifax Academy

Halifax Academy

Pages 2 Pages

CASE STUDY HALIFAX ACADEMY HEADLINES KEY FACTS OFF-SITE 12.48kW £1.1M 3 fabrication of main plant room components took 2 weeks compared to traditional 4-6 solar PV system annually saves 8,262kg of carbon M&E scheme delivered in 30 weeks Project title: Halifax Academy Location: Halifax Client: Bardsley Construction Services: Mechanical & Electrical Contractor: Bardsley Construction Value: £1.1 Million Duration: 30 weeks G&H divisions: Building Services, Fabrication & Sustainability G&H divisions worked together to deliver building services, fabrication and sustainability measuresKEY CONTACT Working to a predesigned scheme, we were asked to provide a range of cutting edg