Case Study
Network Rail
Demolition and reconstruction of the existing road over rail bridge deck during a 52 hour possession. The works also included waterproofing to the new bridge deck, new surfacing and services diversions. Scope of the Works Ashley Road Overbridge is a road over rail bridge on a very busy arterial road which connects the Boscombe area with the A338. Dyer & Butler demolished the existing bridge deck and constructed a new one. The wo