Case Study
Intralox Case Study: PepsiCo | Intralox
Intralox Case Study: PepsiCo | Intralox Background PepsiCo’s Adelaide facility produces 500 tonnes of snacks per week. To fulfill increasing customer demand for half cases rather than full cases, the facility needed greater case handling capacity. Problem The packing hall had a single main line conveyor with several conveyors feeding into it. Frequent jams occurred at the merge points, resulting in production losses which made it difficult for the factory to meet demand. Solution First, Intralox helped redesign the packing hall of the plant. Second, using modular plastic belting and its award winning, patented Activated Roller BeltTM technology in merging, switching, and sorting applications, Intralox comprehensively upgraded the plant’s packing operations. This upgrade will help the plant