Hyperscale Cloud Computing Provider Goes Modular for Rapid Deployment of Needed Capacity

Hyperscale Cloud Computing Provider Goes Modular for Rapid Deployment of Needed Capacity

Pages 1 Pages

A hyperscale cloud provider in Dublin partnered with Vertiv’s E+I Engineering to add 60 MW of capacity through modular data center construction. With only 20 weeks to deliver, the project required rapid design, transport planning, and integration of third-party equipment. E+I supplied 56 modular power skids—each over 22 tons and 85 feet long—plus switch rooms and busbar systems. Factory-controlled assembly enabled Level 3 testing before delivery, cutting on-site labor by 75% and ensuring zero lost-time incidents. The modular approach streamlined approvals, reduced rework, and delivered reliable, scalable infrastructure to meet surging cloud demand.