GLOBE LIFE FIELD

GLOBE LIFE FIELD

Key Achievements Application Technique Market sector Owner Main contractor Engineer Keller business unit (s) GLOBE LIFE FIELD ARLINGTON, TEXAS • McKinney Drilling Company’s (MDC) drilled shaft expertise was key to successful, on-time completion of the permanent earth support portion of the overall stadium construction project. • The project The Texas Rangers organization’s Globe Life Field baseball stadium will replace the existing Globe Life Park. Maximum excavation depth was 85 ft through complex ground conditions composed of sands, clays, sandstones, shales, and alluvium deposits. • The challenge The project was accelerated in order to be complete in time for the 2020 baseball season. While permanent soil nail walls installed by Hayward Baker, Inc. provided the primary means of