Case Study
ASTORIA FERRY LANDING IN HALLETS COVE
Application Technique Owner Market Keller business unit (s) Main contractor Engineer Key achievements ASTORIA FERRY LANDING IN HALLETS COVE ASTORIA, NEW YORK • Mobilized one week from first contact including the completion of pricing, proposal, and contract. • Offered previous experience with similar marine work and scope of work. • Worked multiple shifts and weekends to complete work in accelerated schedule. Drilled Shafts (Caissons) Pre-Drilling Deep Foundations Infrastructure – Ports & Harbors New York City Economic Development Corporation (NYEDC) CM – Skanska USE Building GC – EIC Associates, Inc. McLaren Engineering Group McKinney Drilling Company • The project New York City Economic Development Corporation (NYCEDC) was working hard to improve mob