Emergency Sewer Bypass Required for 90” Line PUMPS • TANKS • FILTRATION • PIPE • SPILLGUARDS 800 742 7246 rainforrent.com BACKGROUND A conservation and reclamation district that provides wastewater treatment services to more than 60 cities and millions of residents in Texas discovered that a 90” sewer line had partially collapsed and taken a good chunk of ground down with it into a large sinkhole. A competent bypass solution was needed, quickly. OUTCOME The customer had to move fast, and was going to use a quick and cheap vendor who said that they could solve the problem with a few 18” pumps outfitted with 24” flanges, delivered in 24 hours. Rain for Rent was also called on and after examining the site requirements, determined that a bypass system of two 30” DV600 pumps would hand