Case Study
DWS EXCEEDS CUSTOMER TARGETS ONvMULTI-WELL PAD
DWS EXCEEDS CUSTOMER TARGETS ON MULTI-WELL PAD Our customer saw numerous drilling and fracing delays on their new 11-well (pressure ranging from ~2000psi ~4500psi) pad. These unforeseen issues were putting their planned Turn In Line (TIL) date and financial targets in jeopardy of not being met. DWS' objective was to recover our customer's lost days by safely and efficiently completing this multi-well pad by applying disruptive HCU innovations. CHALLENGE & OBJECTIVE 2019 Deep Well Services PRE-JOB PLANNING On the seven low-pressure wells, our SIMOP HCU's averaged 2.21 days per well and 3.40 days on the four high-pressure wells which includes production tubing installs. Based on our customer's initial completion forecast, we saved 6.5 days that translated to over 1/2-million dol