Case Study
Delivery of the Phase 1 Earthworks package at the prestigious Chatham Waters Project.
KKB GROUP INNOVATIVE REGENERATION SERVICES Client: Sisk Location: Chatham Waters Site – Chatham Docks Value: £550k Start: February 2017 Completed: March 2017 For more information on KKB services, please contact us at: KKB Group Head Office, Alpha House Laser Quay Culpeper Close, Medway City Estate, Rochester, Kent, ME2 4HU Tel: +44 (0) 1634 717712 | Email: enquiries@kkbgroup.co.uk www.kkbgroup.co.uk Case Study Chatham Waters Phase 1 KKB Group, following a successful competitive tendering process, were engaged by Sisk as their Tier 1 Contractor to deliver the Phase 1 Earthworks package at the prestigious Chatham Waters Project. The works have been delivered ahead of programme and within budget. The works consisted of bulk earthworks of 5,000m3 and stockpile management, 11,000 of