Auburn Street Substation

Auburn Street Substation

Auburn Street Substation Auburn Street Substation, Whitman, MA Substation Upgrade and Line Tap Relocation Project scope included the install of a second auto-transformer and expansion of the existing 115kV south yard, requiring the temporary relocation of 345kV lines (Line 335 and Line 342), to temporary structures. Relocation of the Utilitys 115kV lines (Line 191 and Line 194) was also required. In the 345kV Yard: Additional 345kV bus and (8) n