Case Study
Alternative To Generator Shutdown During Peak Season
MC/TM CS035 The following case describes the successful application of end-winding monitoring technology on two newly commissioned steam turbine generators. This action facilitated their operation through the summer peak demand and helped monitor the performance of subsequent Original Equipment Manufacturer (OEM) modifications. In June 2003, the generator manufacturer notified the utility of a potential serious problem with the phase lug connecto