Innovative Engineers Case study // Acklington Drainage CLIENT CONTRACT VALUE DATE COMPLETE Network Rail £126k Oct 2018 THE CHALLENGE This scheme involved laying the drainage run to the supplied design depths and installation of catch pits and lids at set location throughout the run. The challenge was to achieve the required levels of the drainage within a tight timeframe. WHAT WE DID Stobart Rail & Civils were contracted to carrying out 330 metres of cess and 6 feet drainage on the ECM7 on the down main between 28 miles 460 yards to 28 miles 867 yards on 110mph track. The work was carried out over a 36-hour weekend block with a further two weeks to set up and de-mobilise the site. The primary contractor (PC) supplied all the materials to carry out the planned drainage works wi