Ysbyty Glan Clwyd Hospital

Ysbyty Glan Clwyd Hospital

The challenge It was recognised early in CHt’s assessment that plant replacement would be one of the key drivers for the project, and would require considerable planning input. During one of the initial programming meetings, the site team identified that a large element of enabling works would be required to the existing boilers and natural gas systems to enable their phased removal and replacement. In addition, survey works established that there was insufficient capacity in the medical gas infrastructure to support the new development, and the original riser and distribution network did not have sufficient isolation valves to enable the future phases of asbestos strip out to proceed without causing significant disruption. CHt’s challenge therefore was to provide a new gas supply to the e