Case Study
Waterbury State Office Complex
INTRODUCTION Reconstruction of the Vermont State Offices Complex included construction of a heavily-loaded mat foundation used for a woodchip storage pit within the wood-fired biomass central plant. Project specifications required 8-inch drilled micropiles for compression and tension resistance. Pile installation would be challenged by the working pad level located in the depressed storage pit excavation. GEOTECHNICAL DETAILS Soil conditions