Case Study
Vinyl Sheet Piles Flood Alleviation Scheme, Chivenor
Vinyl Sheet Piles Flood Alleviation Scheme, Chivenor Contract No: C736 Client: BAM Nuttall Location: Chivenor, Nr Barnstaple, Devon Value: Approximately £82,000.00 Summary: Design, supply and install SG425 section vinyl sheet piles to form a permanent cut off wall to a flood alleviation bund wall. Sheet Piling (UK) Ltd were employed by Principal Contractor BAM Nuttall to design, supply and install a vinyl sheet pile cut off wall as part of a floo