Case Study
VACS System Recovered Cones of Tri-Cone Bit and Milled Bridge Plug in One Trip
Benefits ? Effectively retrieved downhole junk and milled bridge plug in one trip ? Ensured successful next step of completion ? Reduced nonproductive time and operation risks Well background and challenges ? Coca, Ecuador, November 2008 ? 7-in. casing to 8,675 ft (2644 m) depth ? 20° well angle ? 8.4 ppg fluid ? CIBPs set to 8,387 ft (2556 m) ? Needed to recover all cones and debris left during a milling job of a CIBP with a t