Case Study
UK Power Network Energy Centre – completion of two 132kV circuits
UK Power Network Energy Centre – completion of two 132kV circuits Description: This project involved the completion of two 132kV circuits to supply a new UKPN energy centre in central London. The installation of the circuits involved laying 1.2km of 132kV cable between the UK Power Network Energy Centre - completion of two 132kV circuitsexisting sub-station on Moreton Street to a new sub-station in Victoria Street. In addition to these electric cables a number of bre optic and telephone cables were also installed. Challenges: The project location in the heart of central London provided many logistical and engineering challenges, as the route of the network passed through key areas of London including; Westminster Cathedral, The House of Commons, Scotland Yard and Victoria Street. A compre