Case Study
Turbidity Barrier & EL6060 for Lock 14 Crowe Dam Rehabilitation
Turbidity Barrier & EL6060 for Lock 14 Crowe Dam Rehabilitation LOCATION: Campbellford, Ontario TIMEFRAME: July 2018 SCOPE OF WORK: Manage sediment during construction on the upstream and downstream side of the rock dam. PROJECT PARTNERS: Owner: Parks Canada, Engineer: Stantec, Contractor: Cegerco, Materials Supplier: Lay eldLayfield Specified: DOT Type II Turbidity Barrier & Anchor System for Sediment Control During construction of rock lled co er dam. EL6060HD Enviroliner Geomembrane – Upstream Co er Dam Lining. Background Information and Challenge Parks Canada Trent Severn Waterway Lock 14 Crowe Bay's dam was constructed in 1913 and due to it's age and the degradation of concrete, required rehabilitation and a bridge replacement. The scope which included bridge demolition and repl