Case Study
Tottenham High Road Bridge
T he existing bridge over Tottenham High Road was approaching the end of its working life and was identified by Network Rail as a structure that needed to be replaced over a blockade during Christmas 2014. To de-risk the blockade works the new track panels were pre- fabricated on the new bridge off site to reduce the physical site works. All materials were supplied loose and built up to the design. The site scope included the removal of the existing track and bottom ballast to enable the old bridge to be removed. The new bridge complete with track panels on deck was installed into its final position followed by the track infill works. Infill panels were built up from loose materials and top ballast installed using on track plant. Once all the rail was in place, weldi