Case Study
The Ostroleka Biomass Boiler House
logo Demanding structures and schedule Large and complex structures for a 55 m tall boiler house. In total, Ruukki manufactured 1,300 tones of steel structures. ? Because of the building height, safety measures had to be taken into special consideration already at the planning stage. All working platforms had to be temporarily secured with railings and all openings covered with thick wooden plates. Around 1 km of railings was used in total. ? Tim