Case Study
Temple University CO Oxidation Catalyst Retro-fit
SCOPE Edison Energy’s Engineering Solutions Team was contracted by Temple University to perform a CO oxidation catalyst retro-fit project. Temple has 20 Caterpillar 3516 natural gas lean burn engines, which are used as peaking units specifically for the University. Edison Energy was responsible for the complete turnkey retro-fit project including design, material procurement, installation and guaranteed performance of CO oxidation catalysts to bring the generating plant into full RICE NESHAP compliance. The installation of the CO Catalyst units took approximately 10 weeks and relied on the complete cooperation of the Temple and Edison Energy teams. Temple University CO Oxidation Catalyst Retro-fit CLIENT Temple University MARKET Institutional › Higher Education OFFERING Energ